East Colfax Bus Rapid Transit (BRT) Project
Latest Update - Oct, 29, 2026
New Since the Last Update
-
New Traffic Shift -- October 30: Traffic between Ivy and Locust streets is scheduled to shift into the center lanes while crews work along the outside edges of East Colfax. Another traffic shift between Bellaire and Elm streets is anticipated by Thanksgiving.
-
Intersection Reopenings: North Kearney Street has reopened, and Grape Street's south-side intersection is open. Additional reopenings are anticipated through November, including Ivanhoe's north side, Fairfax's north side, and Hudson's south side.
-
Upcoming Side-Street Closures: New closures are anticipated throughout November at portions of Ivy, Jasmine, Jersey, Kearney, Krameria, Locust, and Magnolia streets. Residents should watch for changing access and posted detours as construction progresses.
-
Hudson Street Update: The south-side intersection is now expected to reopen by Thanksgiving. Construction on Hudson's north side has been pushed to March 2027.
-
Sidewalk and Utility Work: Crews continue sidewalk reconstruction, utility relocation, curb ramp upgrades, and soil cell installation throughout Mayfair. Work between Forest and Glencoe streets is expected to continue through late November, with additional improvements extending east toward Monaco Parkway.
What to Expect over the Next Two Weeks
Residents should expect changing traffic patterns along East Colfax, including a scheduled October 30 lane shift between Ivy and Locust streets. Additional intersection closures are anticipated in early November as crews continue drainage, sidewalk, utility, and curb ramp improvements
Some previously closed intersections are reopening, while construction shifts to new locations. Residents should follow posted detours, allow additional travel time, and watch for temporary pedestrian and parking restrictions. Upcoming closure dates are estimates and may change as work progresses.
Construction Updates for the Mayfair Neighbors
The BRT Project is one of the largest transportation improvements in Denver in decades. Construction is expected to continue through 2027 and will bring significant changes to East Colfax Avenue, including dedicated bus lanes, new transit stations, pedestrian improvements, streetscape enhancements, and roadway reconstruction.
This page is maintained by Mayfair Neighbors Inc. to help residents understand how East Colfax BRT construction affects the Mayfair neighborhood. Rather than reposting every construction notice, we summarize the updates most likely to affect residents, including traffic changes, pedestrian access, construction progress, and major project milestones.
Quick Resources
For residents seeking additional detail or official project information:
-
East Colfax BRT Construction Hotline: 720-336-0025
Project Overview
The BRT Project extends approximately five miles from downtown Denver to Aurora. Once complete, buses will operate in dedicated center-running lanes, providing faster and more reliable transit service while improving pedestrian safety and accessibility.
Major improvements include:
-
Dedicated center-running bus lanes
-
New BRT stations
-
Improved sidewalks
-
ADA accessibility upgrades
-
New traffic signals
-
Improved crosswalks
-
New street trees and landscaping
-
Utility upgrades
-
Complete roadway reconstruction in many areas
Construction began in late 2024 and is expected to conclude in 2027. Throughout construction, different portions of Colfax will experience varying levels of traffic impacts depending on the phase of work.
Upcoming Milestones
Construction is expected to continue progressing east toward Monaco Parkway throughout the fall. As work advances, residents will see additional sidewalk reconstruction, utility relocation, tree soil cell installation, drainage improvements, pedestrian lighting, and future BRT station construction. Individual intersections will reopen as completed while new work zones continue opening farther east through the corridor. Several intersections are expected to reopen by Thanksgiving or December, while remaining sidewalk and utility work continues. Some intersection work, including Hudson Street's north side, is now scheduled for 2027.
BRT Update: Construction advances as intersections begin reopening
East Colfax BRT construction continues progressing through Mayfair, with crews transitioning between work zones as roadway, sidewalk, drainage, and utility improvements advance. Several intersections are reopening following completed construction, while additional closures and traffic shifts are anticipated throughout November.
Work continues on both sides of East Colfax, including sidewalk reconstruction, curb ramps, soil cells, and utility upgrades. Additional intersection reopenings are expected before Thanksgiving and into December, although schedules remain subject to change.
Past Updates (2026)
During the first half of 2026, construction activity remained primarily west of the Mayfair neighborhood while crews completed utility work, roadway reconstruction, and new BRT stations. Throughout this period, Denver and RTD continued preparing for construction in Mayfair by advancing project planning, operational testing, and future traffic changes.
Notable milestones included:
-
Q3 2026 - July through September
Construction officially entered Mayfair and progressed eastward, bringing utility relocation, drainage work, sidewalk reconstruction, soil cells, intersection closures, and construction of the future Elm Street BRT station. By late September, work had expanded across much of Mayfair toward Monaco Parkway. On September 27, Bus-Only Lane Operations began between Broadway and Colorado Boulevard, allowing Routes 15 and 15L to begin using completed center-running lanes and stations west of Mayfair. -
Q2 2026 - April through June
The project moved closer to Mayfair as construction expanded across the full East Colfax BRT corridor. Denver approved additional project management funding to support construction through completion and released more details about the future roadway configuration. By June, the City announced that construction would soon advance into the Mayfair neighborhood. -
Q1 2026 - January through March
Construction remained primarily west of the Mayfair neighborhood, with minimal direct impacts to Mayfair residents. Crews continued utility and roadway work along the corridor, while RTD began operational testing in preparation for future BRT service.

